Overview
In OpenSpace Track, every task in your task breakdown has components, and each component is assigned a weight that determines how much it contributes to the task’s overall progress percentage.
Component weight
- By default, all tasks are weighted equally toward overall project progress.
- By default, all components within a task are weighted equally.
- Weights can be customized at any time—it’s as simple as changing a number.
- Zero-weight tracking: If you want to track something visually but do not want it to count toward overall progress (e.g., hanger rods already accounted for elsewhere), the component can be assigned a weight of zero. Data is still collected and available.
Recommendation: Consider separating major mechanical equipment (AHUs, chillers, boilers) from terminal devices (trench heaters, chill beams, diffusers) into separate task categories with adjusted weights, to avoid misrepresenting progress.
Example: Suppose a "Plumbing Rough-In" task has three components: hot water piping, cold water piping, and waste piping. By default each counts for 33%. But if hot water piping is a much larger scope on your project, you might adjust the weights to 50%/30%/20%. If waste piping insulation is tracked separately but already accounted for elsewhere, you could set it to 0% weight—the data is still collected, but it does not affect the overall progress percentage.
Next steps
If you have any additional questions please reach out to your OpenSpace Track Implementation Consultant.